AKTOR Leads €120.5m Minagiotiko Dam PPP in Messinia

AKTOR Group-led consortium signs a €120.5m, 25-year PPP contract to build Messinia's Minagiotiko Dam for irrigation and drinking water.

AKTOR Leads €120.5m Minagiotiko Dam PPP in Messinia

A consortium led by AKTOR Group signed a Public-Private Partnership (PPP) contract on Wednesday for the "Study, Financing, Construction, Maintenance and Operation of the Minagiotiko Dam through PPP," a major infrastructure project to be built in the Messinia region of southern Greece.

The contract was signed by Greece's Minister of Rural Development and Food, Margaritis Schinas, and the Chief Operating Officer of AKTOR Group and Chief Executive Officer of AKTOR Construction and AKTOR Holdings, Anastasios Aranitis.

Officials described the project as highly significant, saying it will shield Messinia against the climate crisis, create the conditions for sustainable development in the area for decades to come, and provide a lasting solution to irrigation and drinking water shortages across the wider region by drawing on modern digital water management technology.

AKTOR Group's Chairman and Chief Executive Officer, Alexandros Exarchou, said taking on the landmark project marked a new chapter in the delivery of major infrastructure in Greece, combining improved water management, a focus on the water cycle, the challenges of the climate crisis and stronger cooperation between the public and private sectors. He said this combination amounted to a holistic response to tomorrow's challenges and should guide the company's future direction. Exarchou added that AKTOR Group has the know-how, experience and talent needed to help the country deliver lasting and sustainable solutions to water resource management, and that it is investing systematically in PPP and concession projects as part of its strategy to become a fully integrated infrastructure group.

Project profile

The project carries a construction budget of €120.5 million. The PPP contract runs for 25 years in total: three years for construction, two years to fill the reservoir, and 20 years for operation. The private partner will finance €25 million of the cost, while the public contribution will amount to €29.5 million.

The scheme covers the Minagiotiko Dam and an irrigation network that will serve 35,000 stremmata of land in the municipality of Pylos-Nestoras, within the Messinia regional unit. It will also supply drinking water to the settlements of Lachanada and Foinikounta, in the municipality of Pylos-Nestoras, and Militsa and Vlasaika, in the municipality of Messini.

The dam and reservoir

The Minagiotiko Dam will be built on the Minagiotiko stream, roughly 1.5 to 2 kilometres west of the settlement of Vlasaika, 3.7 kilometres southeast of Kallithea, and 5.5 kilometres upstream of the stream's outlet at Foinikounta. Positioning the dam axis 90 metres downstream of the confluence of the stream's two branches allows for the maximum possible collection of water with the most efficient construction volume.

The structure will be an axisymmetric dam built from compacted embankment with an upstream waterproof facing, standing a maximum of 55.5 metres from its foundation, with a crest length of 225 metres and a crest width of about 10 metres. It will include a built-in frontal spillway 24 metres wide and a stilling basin to safely release floodwaters. The reservoir will hold a total volume of roughly 11 million cubic metres, with a useful water depth of 29 metres and a surface area of about 887 to 889 stremmata at overflow level.

Benefits for the local community

The project is designed to provide sufficient, good-quality irrigation water for 35,000 stremmata of cultivated land, used mainly for olives, outdoor vegetables and greenhouse crops. It will serve the former municipal districts of Evangelismos, Foinikounta, Lachanada and Foiniki, formerly part of the municipality of Methoni, as well as Pidasos, Chomatada, Kallithea and Ampelakia, formerly part of the municipality of Pylos, and Militsi, formerly part of the municipality of Aipeia.

Water supply and network restoration

The project will secure drinking water for the settlements of Lachanada and Foinikounta, in the municipality of Pylos-Nestoras, and Militsa, Vlasaika and Giannoukakaika, in the municipality of Messini, through the construction of a modern water treatment plant with a capacity of 150 cubic metres per hour, covering both current needs and future tourism growth. A dedicated sub-project will also fully restore existing water supply infrastructure and ensure it keeps operating without interruption before, during and after the dam's construction.

Environmental safeguards

The scheme includes a fixed ecological flow of 0.03 cubic metres per second, or 933,120 cubic metres a year, released downstream of the dam to protect the stream's natural ecosystem. Construction will use new-generation materials chosen for their resistance to climate change.

A modern digital project

The scheme will include a smart, efficient irrigation network organised into five irrigation zones, supported by three pumping stations and four storage tanks. Every water intake point will be fitted with an electronic system using a prepaid card for automatic billing through NFC technology and mobile phones.

The project will also feature a central, open-architecture wireless telemetry and remote-control system providing a real-time view of operations through modern network technology. The system will draw on weather forecasts, soil moisture data and crop growth information to cut water use by up to 40% and increase agricultural output.

What happens next

Under the signed contract, construction is set to last three years, followed by two years to fill the reservoir and 20 years of operation.

Test yourself

  1. What is the total construction budget for the Minagiotiko Dam project?

  2. How long does the PPP contract for the dam run?

  3. How much can the project's digital irrigation system reduce water use by, according to the article?

Have your say

Do you think public-private partnerships are a good model for financing major water infrastructure projects?

Where it happened

Pylos, Greece