Greece's Deputy Minister of Infrastructure and Transport, Nikos Tachiaos, said the Thessaloniki Metro's depot planned near the border of the Municipality of Evosmos, above the city's Ring Road, will also function as a passenger station with parking for commuters switching between transport modes. He made the comments in an interview with Radio Thessaloniki.
Tachiaos said the land needed for the depot-station has already been secured. He said the metro extension toward northwestern Thessaloniki remains the project's top priority and has already been presented publicly, with station siting studies well advanced, including the exact locations of above-ground installations. He said the siting plans have been shared with mayors in the area and that technical meetings on station locations are continuing.
Pontou Street link to the airport road
Turning to the eastern side of the city, Tachiaos explained that Pontou Street must be connected to Georgikis Scholis Street, the road leading to Thessaloniki's airport, in order to link up with the rest of the city's road network.
He said the connection runs through a triangular plot of land beyond the Peripheral Trench, within the boundaries of the Municipality of Pylaia-Hortiatis. The municipality has drawn up an urban planning study for the area, which is currently at its second public posting stage. Tachiaos said a future metro station to serve the area must be planned for the point where the new road ends, near the Higher War School.
Mikra as the eastern transfer hub
Tachiaos said the goal is for buses, other public transport and cars travelling from the Michaniona-Peraia corridor and the airport to terminate at a station in Mikra. He described this station as the main transfer hub for eastern Thessaloniki, at least until the metro itself is extended to that side of the city.
He said that once construction of Pontou Street is finished, the Thessaloniki Suburban Railway Organisation and the Thessaloniki Urban Transport Organisation plan to increase the frequency of bus routes to Mikra. Nea Elvetia, he added, will remain the main route for Panorama, areas within the Municipality of Thermi, and journeys to and from the Halkidiki peninsula.
Tachiaos said the Mikra terminal station is not a priority for the Municipality of Kalamaria alone. He said it matters for the whole city.
A longer-term eastward extension
Looking further ahead, Tachiaos set out how the metro itself could eventually be extended eastward. He said studies carried out so far show the airport alone would not generate enough passenger traffic to justify an extension on its own. For that reason, he said, planners are also looking at including the Patriarchiko area, where the Mediterranean Cosmos shopping centre is located, and further west the Diavalkanikou area, which also has large concentrations of commercial activity, before the line would turn onto Georgikis Scholis Street toward the airport.
Tachiaos stressed that this is still future planning and will depend on funding becoming available. He said the metro is being built in stages, with northwestern Thessaloniki as the first goal, but that groundwork needs to start now so that any new roads built in the meantime are designed in a way that allows the metro to run beneath them later. He said it is far safer, both for the metro itself and for nearby buildings, for the line to pass underneath roads rather than elsewhere.
Pontou Street construction timeline
On the Pontou Street project itself, Tachiaos said the construction contract was signed about three weeks earlier, with a contractual completion period of nine months. He said the contractor is finishing the final technical studies and that the first two construction sites will be set up before Christmas.
The Thessaloniki Metro is Greece's second underground rail system after the one in Athens, and its first line began carrying passengers in late 2024 following years of delays. Evosmos, Kalamaria and Pylaia-Hortiatis are municipalities within the greater Thessaloniki urban area.