Regional authorities in southern Belgium have suspended construction of a large Google data centre after finding that the American technology company had altered its original building plans without the required planning permission.
Inspectors who visited the site found the building was nearly finished, with the main construction work already completed, even though the relevant permit had been rejected, Raphael Stokis, an official with the Wallonia region, told the public broadcaster RTBF.
Around 300 workers were given a verbal order to stop work, which was later confirmed to Google in writing, Stokis said.
Google said in a statement that it remained committed to maintaining an open and constructive dialogue with the regional authorities, according to the British newspaper The Guardian.
Design changes and water use at centre of dispute
The case dates back to 2025, when Google applied to modify its original design for the project, with the biggest change being a switch from an air-cooling system to a water-cooling system.
The application was initially approved by local authorities, but the decision was later withdrawn following objections from residents and campaign groups. Google appealed against that decision, and a court ruling is expected early next year.
The complex under construction covers around 3 hectares within a business park spanning 50 hectares in total, built on the site of a former coal mine in the Aiseau-Presles area, about 15 kilometres west of Charleroi. It is one of three data centre facilities Google had originally planned to build at the site.
Nicolas Yernaux, a spokesperson for the regional government, told the AFP news agency on Friday that a report is being filed with prosecutors describing a "serious violation," since a 3-hectare building is reportedly being constructed illegally.
Greenpeace raises environmental concerns
The environmental group Greenpeace brought renewed attention to the issue this week, publishing a report with aerial drone footage that it said showed Google continuing construction work despite lacking the necessary permits.
Greenpeace said the technology giant was continuing the work even though the latest version of the planning permit for the data centre had been withdrawn in August, and said it had filed an urgent appeal with the relevant local planning authorities.
The group also warned about the environmental impact of expanding energy-intensive digital infrastructure, saying the climate crisis would further intensify in the region and that uncontrolled construction of energy-hungry giant facilities could not be allowed.
From three smaller centres to one large complex
The original permit Google received in 2024 covered the construction of three smaller data centres that would have used air-cooling systems.
In 2025, however, the company asked to merge two of the facilities into a much larger complex while also switching the cooling technology to water cooling.
The new plan called for pumping 600 cubic metres of water an hour from the nearby Sambre river, which triggered strong objections over the potential impact on the region's water resources, particularly during periods of drought.
The regional administration had initially approved the changes in April. But residents and protest groups filed appeals, and in August Wallonia's infrastructure minister, Francois Desquesnes, withdrew the amended permit, citing concerns about the risk of water shortages.
Google then took the matter to Belgium's Council of State, with a ruling expected on January 7.
New front in Europe's data centre expansion
The legal dispute in Belgium is another obstacle for Google in the European market, as major technology companies accelerate their investment plans for data centres to meet growing demand driven by artificial intelligence.
A similar issue has emerged in Finland, where a criminal investigation began in October into possible breaches of environmental law linked to a planned Google data centre in a rural area of the country's north. Work there has also been suspended until the required environmental impact assessments are completed.
What happens next
Belgium's Council of State is expected to rule on Google's appeal over the revoked permit on January 7, and a separate court verdict on the earlier planning dispute is expected early next year.
Test yourself
Why did Wallonia's authorities order a halt to the Google data centre?
What cooling change did Google propose that drew objections?
What did Greenpeace allege in its report this week?
Have your say
Should regional authorities have the power to halt large tech data centre projects over water use concerns?
Where it happened
Charleroi, Belgium